The yields to remember
| Bag size | Makes (mixed) | Bags per yd³ | Bags per m³ |
|---|---|---|---|
| 80 lb | 0.60 ft³ | 45 | 59 |
| 60 lb | 0.45 ft³ | 60 | 79 |
| 50 lb | 0.375 ft³ | 72 | 95 |
| 40 lb | 0.30 ft³ | 90 | 118 |
These are the standard published yields for common US bagged mixes. Whatever you are pouring, bags = volume in ft³ ÷ yield, rounded up — then add waste (10% is a sound default) before you shop, not after you run short.
Bag table: slabs 4 in thick
| Slab size | Volume | 80 lb bags | 60 lb bags |
|---|---|---|---|
| 4 × 4 ft | 5.33 ft³ (0.20 yd³) | 9 | 12 |
| 6 × 6 ft | 12.00 ft³ (0.44 yd³) | 20 | 27 |
| 8 × 8 ft | 21.33 ft³ (0.79 yd³) | 36 | 48 |
| 10 × 10 ft | 33.33 ft³ (1.23 yd³) | 56 | 75 |
These counts are exact volumes with no waste added, so you can see the raw scale. The bag calculator adds your waste allowance on top.
Worked example: four fence-post holes
Post holes 12 in across and 3 ft deep: each hole is π × 0.5² × 3 = 2.36 ft³; four holes are 9.42 ft³. In 80 lb bags: 9.42 ÷ 0.60 = 15.7 → 16 bags. In 60 lb bags: 9.42 ÷ 0.45 = 20.9 → 21 bags. (The post itself displaces some concrete, but the hole is never a perfect cylinder — the two effects roughly cancel, and one spare bag beats a shallow post.)
Bags or a ready-mix truck?
- Under ~0.25 yd³ (about 11 bags of 80 lb): bags, comfortably.
- 0.25–0.75 yd³: bags are feasible but it is a real workout — 20–34 bags of 80 lb is 1,600–2,700 lb of dry mix to move twice. Price both options.
- Over ~1 yd³: ready-mix, unless access makes a truck impossible. 45+ bags mixed by hand will still be setting while you are mixing the last third.
Whichever route you take, the volume maths is the same — start from the concrete calculator, and let it add the waste.
Two mistakes that waste bags
- Over-watering. Extra water makes mixing easier and concrete weaker; it does not meaningfully stretch a bag. Use the water quantity printed on the bag.
- Counting bags by weight of the pour. A cubic yard of placed concrete weighs about 4,000 lb, but that includes water and the fact that dry mix bulks differently — dividing 4,000 by 80 gives 50 bags, not the correct 45. Always work from yield volume, never from weight.